Dubai Trams are back on track
Car News

Dubai Trams are back on track

·
May 8,2013
·
1 min read

Tags:

Dubai Tram Construction Progress: A New Public Transportation System

Dubai Tram Construction

Overview of the Tram Project

About 5 years ago, the construction of the Dubai trams by Al Sofouh was announced. Unfortunately, the global crisis led to significant delays in the project.

Current Status of Construction

Finally, the work is back on track, with construction resuming and a new era of public transportation on the horizon. The first tram vehicles are expected to arrive in December of this year.

Project Budget and Timeline

The tram project has a budget of Dh 3.18 billion. The completion of the first stage is anticipated by the autumn of next year, which will link:

  • Dubai Marina
  • Mall of the Emirates
  • Dubai Internet City

Completion Progress

According to a progress report by Mattar Al Tayer, Chairman of the Roads and Transport Authority, significant milestones have been achieved:

  • More than 50% of the overall project is completed.
  • 90% of the tram depot, which is the most advanced section of the project, has also been finalized.

As reported by the National newspaper.

Got a comment? Post it below:


Do you want to sell your car for FREE?
We have everything that makes it easier for you to sell your car on our platform quickly
Sell your car 100% absolutely free on YallaMotor.
200+ Cars Sold Everyday.
115,000+ Satisfied Sellers.
500,000+ Monthly Buyers.